Engineering Division

FY20-24 Sidewalk & ADA Ramp CDBG Project continued curb ramps along Meridian Ave. have been constructed and contractor is completing asphalt improvements. Contractor to continue to construct more ramps citywide in the following weeks. Grevelia and Berkshire Pocket Parks construction continues. Grading and compaction operations are nearly complete at Berkshire Pocket Park.

Curb Ramp & Pocket Park Update

Operations

Public Works Operations has been actively repairing potholes throughout the City and preparing sidewalks for repairing along Montrose Ave. and Laurel Ave.

Sidewalk Repairs